- Nerdy Turtlez A Platform Owned By Absas Solutions General Aptitude Interview Questions
- Nerdy Turtlez A Platform Owned By Absas Solutions Trainee Interview Questions
- Nerdy Turtlez A Platform Owned By Absas Solutions Personal Questions round Interview Questions
- Nerdy Turtlez A Platform Owned By Absas Solutions HR Interview Questions
- Nerdy Turtlez A Platform Owned By Absas Solutions Lead Interview Questions
6 miles per hour…….
actually hat fell when they were 1 mile away from starting
and total time hat takes to travel to the starting point is
10 minutes ( 5 + 5 ).so, 1 miles per 10 minutes thats why 6
miles per hour
The answer probably lies in finding the in-centre of the
traingle. Bisect all the angles of the triangles and the
point where these angle bisectors meet gives u the point P
225
p = prob(1st digit not 7)*prob(2nd digit not 7)*prob(3rd
digit not 7)
=(8/9)*(9/10)*(9/10)
=0.72
Sandhya had it right except that there are 900 numbers
between 100 and 999 inclusive (not 899).
50 each
3x -y = 100
4x-2y = 100
40
11
Circular Track sis of 11 km
Speed of Mens are
4 , 5.5 , 8 km/hr
Time at Which they are at starting Points again
11/4 , 11/5 , 11/8
11/4 , 2.2 , 11/8
We need to find LCM of these
to find at what time they Meet again at starting point
LCM 11 * 2 = 22
After 22 Hrs they will meet at starting point
8 games They played
A own 3 games = 18 Rs
B loss 3 Rs and own 1 games i,e 9(A own 3 Games)-6(B own
1 game)=3
c own 12 Rs and loss 4 games(A own 3+b own 1) and own 4
games i.e 24(own)-12(loss)
so totally A own 3 games
B own 1 game
c own 4 games
=8
To solve this problem, we can break it down into steps:
Step 1: Determine the individual rates of work for A, B, and C.
If A needs 8 days to finish the task, then their work rate is 1/8 of the task per day.
If B needs 12 days to finish the task, then their work rate is 1/12 of the task per day.
If C needs 16 days to finish the task, then their work rate is 1/16 of the task per day.
Step 2: Calculate the combined work rate of A and B.
If A works for 2 days, their contribution will be 2 * (1/8) = 1/4 of the task completed.
If B works until 25% of the job is left for C, then they will complete 75% of the task.
Step 3: Calculate the time it takes for B to complete 75% of the task.
Since B’s work rate is 1/12 of the task per day, it will take B (75%)/(1/12) = 9 days to complete 75% of the task.
Step 4: Calculate the remaining work for C.
If B completes 75% of the task, then the remaining work for C is 100% – 75% = 25% of the task.
Step 5: Calculate the time it takes for C to complete the remaining work.
Since C’s work rate is 1/16 of the task per day, it will take C (25%)/(1/16) = 4 days to complete the remaining 25% of the task.
Step 6: Calculate the total time required.
A worked for 2 days, B worked for 9 days, and C worked for 4 days, totaling 2 + 9 + 4 = 15 days.
Therefore, it will take a total of 15 days for A to work for 2 days, B to work until 25% of the job is left, and C to complete the remaining work.
5*(root2)
10%
D
2*3(15+4)=114
114*1/2=57 rs