Answer:50.24
Explanation:
Area of a circle =π*r*r
616=π*r*r
r*r= 616÷3.14
r*r =196
r =13
Circumference of a circle= 2*π*r
=2*π*13
=16*3.14=50.24
C is grand child of A
d
5 trains
4/5
perimeter of rectangle = 2(l+b)
given l abd b as 18 cm and 26 cm
therefore perimeter of rectangle = 2(44)
perimeter of circle = 2*pi*r
given 2*pi*r=2(l+B)
i.e, 2*(22/7)*r= 2(44)
(22/7)*r=44
r=14 cms
area of the circle = pi*r*r
=(22/7)*14*14
=616 sqcm is the answer
sister
area is given by Area of Rectangle = Length of Rectangle*(sqrt((Diagonal of Rectangle^2)-(Length of Rectangle^2)))
so substituting we get area=4*(sqrt((25-16)))
area=4*(sqrt(9))
since area cannot be negative hence we take sqrt of 9 as 3 (as sqrt of 9 is 3 and -3 as well)
area=4*3=12m^2
3 hours ago.
Thin candle melts 3/4 in 3 hours leaving 1/4
Where as in the same time thick candle melts 3/6 leaving 3/6 which is 1/2. Now thick candle is exactly twice than the thin candle.
Or via modeling:
We need to find time at which the length of the thin candle is half the thick candle. Let x be the time. Thin candle melts at 1/4 an hour and thick candle melts at 1/6 an hour. In x hours they melt at x/4 and x/6 respectively. What’s left will be 1 – x/4 and 1 – x/6. We need to find x at which :
2 * (1 – (x/4)) = 1 – (x/6)
This equation results in x = 3
9 days
To solve this problem, we can break it down into steps:
Step 1: Determine the individual rates of work for A, B, and C.
If A needs 8 days to finish the task, then their work rate is 1/8 of the task per day.
If B needs 12 days to finish the task, then their work rate is 1/12 of the task per day.
If C needs 16 days to finish the task, then their work rate is 1/16 of the task per day.
Step 2: Calculate the combined work rate of A and B.
If A works for 2 days, their contribution will be 2 * (1/8) = 1/4 of the task completed.
If B works until 25% of the job is left for C, then they will complete 75% of the task.
Step 3: Calculate the time it takes for B to complete 75% of the task.
Since B’s work rate is 1/12 of the task per day, it will take B (75%)/(1/12) = 9 days to complete 75% of the task.
Step 4: Calculate the remaining work for C.
If B completes 75% of the task, then the remaining work for C is 100% – 75% = 25% of the task.
Step 5: Calculate the time it takes for C to complete the remaining work.
Since C’s work rate is 1/16 of the task per day, it will take C (25%)/(1/16) = 4 days to complete the remaining 25% of the task.
Step 6: Calculate the total time required.
A worked for 2 days, B worked for 9 days, and C worked for 4 days, totaling 2 + 9 + 4 = 15 days.
Therefore, it will take a total of 15 days for A to work for 2 days, B to work until 25% of the job is left, and C to complete the remaining work.
w(drown)
130
520 = 26 * 20 = 2 * 13 * 22 * 5 = 23 * 13 * 5
Required smallest number = 2 * 13 * 5 = 130
130 is the smallest number which should be multiplied with 520 to make it a perfect square.
Because from there i can do more and learned more too