A die is thrown twice n(s)=36
The probability of getting same number is (1,1)(2,2)(3,3)
(4,4)(5,5)(6,6) i.e n(A)=6
Ans. P(A)=n(A)/n(s)
= 6/36
=1/6.
So, The Answer is 1/6
It is due to the counter clockwise motion of the motor. The motor rotates in the counter clockwise direction the blades of the fan are attached to the motor hence the blades rotates in the anti clockwise direction. So it is due to the motor rotation the fan rotates in counter clockwise direction.
Statements :
All film stars are playback singers. All film directors are film stars.
Conclusions :
I. All film directors are playback singers.
II. Some film stars are film directors.
Both conclusion follows
12
4
5/55*100=9.09% defective eggs
To solve this problem, we can break it down into steps:
Step 1: Determine the individual rates of work for A, B, and C.
If A needs 8 days to finish the task, then their work rate is 1/8 of the task per day.
If B needs 12 days to finish the task, then their work rate is 1/12 of the task per day.
If C needs 16 days to finish the task, then their work rate is 1/16 of the task per day.
Step 2: Calculate the combined work rate of A and B.
If A works for 2 days, their contribution will be 2 * (1/8) = 1/4 of the task completed.
If B works until 25% of the job is left for C, then they will complete 75% of the task.
Step 3: Calculate the time it takes for B to complete 75% of the task.
Since B’s work rate is 1/12 of the task per day, it will take B (75%)/(1/12) = 9 days to complete 75% of the task.
Step 4: Calculate the remaining work for C.
If B completes 75% of the task, then the remaining work for C is 100% – 75% = 25% of the task.
Step 5: Calculate the time it takes for C to complete the remaining work.
Since C’s work rate is 1/16 of the task per day, it will take C (25%)/(1/16) = 4 days to complete the remaining 25% of the task.
Step 6: Calculate the total time required.
A worked for 2 days, B worked for 9 days, and C worked for 4 days, totaling 2 + 9 + 4 = 15 days.
Therefore, it will take a total of 15 days for A to work for 2 days, B to work until 25% of the job is left, and C to complete the remaining work.
9654
2, 6, 12, 72, 824
2
6*2=12
12*6=72
72*12=864
2*3*5*7*11*13*17*19=9699690
I am looking for a qualified chartered accountant in my profile who is known for his excellence in the field.
Answer: Option C two
FASHION= FOIHSAN
It is F-ASHIO-N to F-OIHSA-N.
So PROBLEM will be P-ROBLE-M,
the answer is PELBORM.