-Total /n=80
– x/5=40
x=200
Total/n=y/n
y-x/n-5=90
80n-200=90(n-5)
80n-200=90n-450
450-200=10n
n =25 (students) write exam
B
Put a= 4, b = 2 in the equation and multiplying by 2/2 then you will get same value in right hand side. It mean a is 2a which mean b<a
3600 sec in 1 hr.. 1000 M in 1 km so to covert m/s to km /hr you multiply the value with (3000/1000) .. so 3000 divided by 1000 will give you 18/5 it’s like constant value.. to convert m/s to km/ hr we can use this 18/5.. hope you understand
26
7,9,11
Total game played= 60
%won =30%
Total won= 60*30/100 i.e. 18
now team plays x games and win all of those to increase the
average to 50%.
So,
(60+x)*50/100=18+x
(60+x)/2=18+x
60+x=36+2x
24=x
So the final answer is 24.
Is it not 24?
1, 2, 4, 13, 31, 112,?
This series is written in base 5 numbers for decimal nos of 1,2,4,8,16,32,64
so next number is 224 .
224 in base 5 = 64 in base 10.
so 224 is next number.
To solve this problem, we can break it down into steps:
Step 1: Determine the individual rates of work for A, B, and C.
If A needs 8 days to finish the task, then their work rate is 1/8 of the task per day.
If B needs 12 days to finish the task, then their work rate is 1/12 of the task per day.
If C needs 16 days to finish the task, then their work rate is 1/16 of the task per day.
Step 2: Calculate the combined work rate of A and B.
If A works for 2 days, their contribution will be 2 * (1/8) = 1/4 of the task completed.
If B works until 25% of the job is left for C, then they will complete 75% of the task.
Step 3: Calculate the time it takes for B to complete 75% of the task.
Since B’s work rate is 1/12 of the task per day, it will take B (75%)/(1/12) = 9 days to complete 75% of the task.
Step 4: Calculate the remaining work for C.
If B completes 75% of the task, then the remaining work for C is 100% – 75% = 25% of the task.
Step 5: Calculate the time it takes for C to complete the remaining work.
Since C’s work rate is 1/16 of the task per day, it will take C (25%)/(1/16) = 4 days to complete the remaining 25% of the task.
Step 6: Calculate the total time required.
A worked for 2 days, B worked for 9 days, and C worked for 4 days, totaling 2 + 9 + 4 = 15 days.
Therefore, it will take a total of 15 days for A to work for 2 days, B to work until 25% of the job is left, and C to complete the remaining work.
DISSENTIAL