1^1,2^2,3^3,4:^4,5^5,6^6
1,4,27,256,3125,46656
Answer: 66.67 km approx.
Solution:
Let the first train A move at u km/h.
Let the second train B move at v km/h.
Let the distance between two trains be d km
Let the speed of bee be b km/h
Therefore, the time taken by trains to collide = d/(u+v)
Now putting all the known values into the above equation, we get,
u = 50 km/hr
v = 70 km/hr
d = 100 km
b = 80 km/hr
Therfore, the total distance travelled by bee
= b*d/(u+v)
= 80 * 100/(50+70)
= 66.67 km (approx)
s=a+(a+10)+(a+10+10)+(a+10+10+10)
s=4a+60
a=(s-60)/4
Profit one with 3 & 2 nd 2.4
Had is correct ! Anil went in right direction but ended up
with wrong answers
Soln: B lied ( see anil’s comment ) which implies B has not
stolen mule. So B could steal camel or sheep.
1) Lets assume B stole camel.
In that case, A lies ( refer – A says “B had stolen sheep”
), which implies A had stolen sheep ( becoz a lier cant
steal mule ). So A->sheep B->camel C->mule. But this cant
happen because C cant lie ( refer – C says ” B had stolen
mule” ).
2) Lets assume B stole sheep.
In that case, A is true ( refer – A says “B had stolen
sheep” ), which implies A had stolen mule. So A->Mule
B->Sheep C->camel. Here C lies ( refer – C says ” B had
stolen mule” )
SO ANS: answer A- mule, B-sheep, C camel
240-24
650-?
?=24*650/240
65SEC
Answer:
11 days.
Step-by-step explanation:
In the question,
Time taken by Ramesh to finish a piece of work = 20 days
Time taken by Sushil to finish a work = 25 days
Time for which they worked together = 5 days
Sushil left after = 5 days
So,
One day work of Ramesh is,
One day work of Sushil is,
So,
Work done in 5 days is given by,
Therefore, Remaining work is given by,
Now, as the Sushil left the remaining work was done by Ramesh,
Time taken by Ramesh for the remaining work is,
Therefore, the remaining work will be completed in 11 days by Ramesh.
Suppose that total 100 employees are in company….. out of that 35 are man and remaining 65 are women.
20% of man 35 = 20*35/100
40% of women = 40*65/100
total employees = 7+26 = 33 out of 100
so, Ans = 33 %
19, 26, 33, 46, 59, 74, 91
Answer 33
Adding 7,9.13,15,17
Correct is 35
at least 2, at most 4….
2 if you get lucky the first 2 times you draw a jelly bean, 4 would be if in the first 3 tries you get one of each color and the next draw will get you 2 of the same color
South-West
I agree with @TUMWINE PETER
6 pairs of earrings. So 12 earrings.
The total has to be 26, so let’s say there’s 6 pairs of earrings and the number of pairs has to be 4 less than the number of rings. So that would make 10 rings. The 10 rings has to be 2 1/2 greater than the number of pins. So you would divide 10/2.5 = 4 Pins. That would equate to a total of 12 earrings, 10 rings, and 4 pins. A total of 26 pieces.
Friends,
The Answer given by ‘Gaurav Sharma’ is correct and
the approach (bottom to top) suggested by ‘Shailesh’ is
good. But with minor correction we can arrive the solution
using this approach:
After 5th loot, No. of breads left = 3
after 4th loot, no. of breads left = (3+0.5)x2 = 7
after 3rd loot, no. of breads left = (7+0.5)x2 = 15
after 2nd loot, no. of breads left = (15+0.5)x2 = 31
after 1st loot, no. of breads left = (31+0.5)x2 = 63
So, before 1st loot, no. of breads left = (63+0.5)x2 = 127