- Thomaskelly software associates General Aptitude Interview Questions
- Thomaskelly software associates Trainee Interview Questions
- Thomaskelly software associates Personal Questions round Interview Questions
- Thomaskelly software associates HR Interview Questions
- Thomaskelly software associates Lead Interview Questions
Its very simple..
consider the fraction of s in the mixture = 1/3
So if we add one more R the the fraction wil be = 1/4
Automaticaly S becomes 25% of the mixture
1
6=1x2x3
24=2x3x4
60=3x4x5
120=4x5x6
210=5x6x7
336=6x7x8
35000
12
16.8 sec
4, 5, 15, 49, 201, 1011, 6073
Correct option is A)
2nd term =(1stterm×1+2)=(4×1+2)=6
3rd term =(2ndterm×2+3)=(6×2+3)=15
4th term =(3rdterm×3+4)=(15×3+4)=49
5th term =(4thterm×4+5)=(49×4+5)=201 and so on
∴5 is wrong.
3 years – 3000.0
6 years – 4500.0
9 years – 6750.0
12 years – 10125.0
15 years – 15187.5
18 years – 22781.25
To solve this problem, we can break it down into steps:
Step 1: Determine the individual rates of work for A, B, and C.
If A needs 8 days to finish the task, then their work rate is 1/8 of the task per day.
If B needs 12 days to finish the task, then their work rate is 1/12 of the task per day.
If C needs 16 days to finish the task, then their work rate is 1/16 of the task per day.
Step 2: Calculate the combined work rate of A and B.
If A works for 2 days, their contribution will be 2 * (1/8) = 1/4 of the task completed.
If B works until 25% of the job is left for C, then they will complete 75% of the task.
Step 3: Calculate the time it takes for B to complete 75% of the task.
Since B’s work rate is 1/12 of the task per day, it will take B (75%)/(1/12) = 9 days to complete 75% of the task.
Step 4: Calculate the remaining work for C.
If B completes 75% of the task, then the remaining work for C is 100% – 75% = 25% of the task.
Step 5: Calculate the time it takes for C to complete the remaining work.
Since C’s work rate is 1/16 of the task per day, it will take C (25%)/(1/16) = 4 days to complete the remaining 25% of the task.
Step 6: Calculate the total time required.
A worked for 2 days, B worked for 9 days, and C worked for 4 days, totaling 2 + 9 + 4 = 15 days.
Therefore, it will take a total of 15 days for A to work for 2 days, B to work until 25% of the job is left, and C to complete the remaining work.
Statements :
All poles are guns. Some boats are not poles.
Conclusions :
I. All guns are boats.
II. Some boats are not guns.
C
7 : 3