36, 54, 18, 27, 9, 18.5, 4.5
The local value of 7 in the number is at 10000 so 7×10000 and face of 7 is 7
So 70000 -7 so the answer is C 69993
26
30/100*142.85 = approx. 100
so ans is 42.85
324:400:576?
18×18:20×20:24×24:26×26
324:400:576:676
SHADOW
8, 13, 21, 32, 47, 63, 83
47 is answer by consecutive adding of
8+5=13
13+8=21
21+11=32
32+14=46
46+17=63
240.
X : (3000 x 8) + (2000 x 4) = 32000
Y : (4000 x 8) + (5000 x 4) = 52000
X:Y = 32000:52000 = 8:13
8k + 13k = 630
k = 30
X:8 x 30 = 240
3 miutes
225
32000
610 × 717 × 1127
= (2 × 3)10 × 717 × 1127
= 210 × 310 × 717 × 1127
Number of prime factors in the given expression
= (10 + 10 + 17 + 27)
= 64
2 Leap years
+2 to tuedsay
Thursday is the correct answer
Pen
To solve this problem, we can break it down into steps:
Step 1: Determine the individual rates of work for A, B, and C.
If A needs 8 days to finish the task, then their work rate is 1/8 of the task per day.
If B needs 12 days to finish the task, then their work rate is 1/12 of the task per day.
If C needs 16 days to finish the task, then their work rate is 1/16 of the task per day.
Step 2: Calculate the combined work rate of A and B.
If A works for 2 days, their contribution will be 2 * (1/8) = 1/4 of the task completed.
If B works until 25% of the job is left for C, then they will complete 75% of the task.
Step 3: Calculate the time it takes for B to complete 75% of the task.
Since B’s work rate is 1/12 of the task per day, it will take B (75%)/(1/12) = 9 days to complete 75% of the task.
Step 4: Calculate the remaining work for C.
If B completes 75% of the task, then the remaining work for C is 100% – 75% = 25% of the task.
Step 5: Calculate the time it takes for C to complete the remaining work.
Since C’s work rate is 1/16 of the task per day, it will take C (25%)/(1/16) = 4 days to complete the remaining 25% of the task.
Step 6: Calculate the total time required.
A worked for 2 days, B worked for 9 days, and C worked for 4 days, totaling 2 + 9 + 4 = 15 days.
Therefore, it will take a total of 15 days for A to work for 2 days, B to work until 25% of the job is left, and C to complete the remaining work.
C